Leaking joints reduced to less than
one per cent, and substantial cost savings
- in excess of £100,000 by avoiding re-work alone - have been achieved
on the BP Magnus EOR (Enhanced Oil Recovery) project, by Vector International
working with the Wood Group. The successes are the result of a new leak reduction
management service offered by Vector.
This new approach to leak reduction - involving close management of every stage
from joint component manufacture and supply to installation - has been successfully
proven to see leaking joints plummet to less than one per cent on commissioning.
This is significantly lower than is often observed - according to HSE data cited
by UKOOA recently, 17 per cent of hydrocarbon releases can be attributed to leaking
joints and 25 per cent of leaks occur on start up.
Time, and therefore cost, savings were substantial as a result of implementing
Vector's leak reduction initiative, both by minimising the repair and modification
work needed offshore, and by ensuring leak-free joints first time - avoiding
delays while leaks were rectified. Not only can the contractor benefit from completing
in line with (or ahead of) commissioning deadlines, but any potential loss of
production caused while repairing leaking joints is also virtually eliminated.
Among the key elements of the initiative is the inspection of all joint components
- Vector connectors and associated interfacing equipment - on-shore, at each
stage of production and testing, prior to shipment. This guarantees that all
components are in working order, and is crucial to the high levels of leak-free
connections first-time, which generated the significant cost savings.
"By inspecting and testing all joint components at every stage, we're able
to identify any problems at a point at which it costs significantly less to rectify
them - the cost to repair or replace components can be ten to fifteen times greater
once offshore - and before transportation and initial installation costs have
been incurred," explains Ian Robinson, sales and marketing director at Vector
International. "It means all components arrive offshore fit for purpose.
Furthermore, by inspecting before the goods have been supplied to the project,
the cost of any re-work remains the onus of the supplier or fabricator," he
adds.
Extensive training is a further key element of the management service, so that
all those involved in handling the connection components at any stage - start
of project to final installation and commissioning - fully understand the requirements
of the joint and its make-up. This ensures that damage commonly caused unwittingly
in construction, testing, transportation or assembly (particularly of the sealing
surfaces) is avoided, and correct and effective installation achieved.
"Whether by mishandling, chemical cleaning, over-torquing, or many other
ways - how easily damage can be caused and the severely detrimental effect it
has on joint integrity (even an apparently 'minor' defect) is often simply not
understood, so effective competence training can make all the difference," Robinson
explains. "Indeed, the key role of training in successful joint management
is stressed in the UKOOA guidelines launched in the autumn - a further recognition
of its importance."
Offshore, the availability of trained, skilled and experienced Vector technicians
as part of the leak reduction service allows all sealing surfaces to be thoroughly
checked, and ensures that joints are assembled in accordance with Vector's operational
standards. It also enables any non-conformances and necessary remedial actions
to be dealt with rapidly.
Moreover, significant time and cost savings were achieved on BP Magnus EOR through
use of Vector's new RIT (Reverse Integrity Testing) rings - a means of testing
and verifying individual joint integrity, in-situ, as the joints are installed,
without having to conduct a full line leak-test. What's more this method uses
far lower levels of test medium than a traditional full system test, saving money
and improving safety, especially when using a traditional gas leak test. RIT
rings are also proven to be a more effective method of detecting leaks than a
traditional test.
Wood Group project manager on BP Magnus EOR Terry Daniels says: "The use
of RIT rings to test flowline and compressor discharge pipework decreased installation
and commissioning times and gave confidence in the system's high pressure containment
integrity."
The benefits and resounding success of the leak reduction initiative were apparent
on commissioning BP Magnus EOR. "That no clamp connector joint failures
were reported during commissioning more than justifies the up-front cost of the
service, which is significantly less than the potential cost of repairs that
would otherwise have been required as each leaking joint was discovered," Daniels
enthuses.
Drewan Mouat, BP's offshore completions manager adds: "Traditionally problems
such as leaking joints discovered during commissioning can mean significant delays
in start-up, and of course lost production - at considerable expense. The trouble-free
start-up the Magnus EOR project achieved by ensuring no leaking joints first-time
justified the cost of the inspection, training, testing, and management services
provided by Vector. It's been a great success, and should definitely be adopted
by all projects."
|
|
|